GUILLIMAN PRODUCTION PROGRESS

March 2 2019
QC Factory 1st Production Samples

QC Factory 1st Production Samples

After sending the prototypes to the factory, the first step is for them to produce a production-ready sample while re-engineering the parts for assembling and ease of production purposes. This is also the time for the factory to match the coloring and looks from what HMO provided to them with the master prototype.

May 7 2019
Fixing Casting Results

Fixing Casting Results

Many times when we re-engineered the part for casting, many issues will arise as well, like surfaces not being smooth, or there could be possible shrinkage and parts not fitting with each other. This is the moment for HMO to work with the factory to identify all these issues.

June 30 2019
Casting Has Started!!

Casting Has Started!!

Many parts are being cast, and going through testing on the materials and quality QC with HMO.

August 20 2019

Foam Box Design

After engineering is done and approved. We can now move into cutting and packing the parts together. This step will actually take lots of work due to drop testing and fitting of all the parts.

November 12 2019
Packaging Box Design

Packaging Box Design

Finally, we get the design finish and sending in for GameWorkshop for Approval. Hoping all will be smooth and get this design to sent out for test printing right after. The white marble goes well with the statue base when displaying together.

November 18 2019
Preparing Base Coat

Preparing Base Coat

Many parts are coming out of the ovens now, we are adding the base coat on them to get all ready to be painted soon. Really exciting to see all the parts coming together.

November 21 2019
Painting Painting Painting….

Painting Painting Painting….

There are just so many parts to be painted. Go Factory Go!!

January 2 2020
Package Box First Print Testing

Package Box First Print Testing

First print testing for our Guilliman’s package box after the approval on the design from Game Workshop. There are still many things to test and consider, especially for that gold foil frame UV printing.

January 8 2020
More and More to be Painted

More and More to be Painted

Look at all the parts Guilliman have, Factory is hard at work pumping out all the parts to be painted to meet up with HMO’s shipping timeline.